ERP Upgrade Go-Live Collapsed, Rescued and Completed — Operations Restored Within 18 Days
A Hamilton food wholesaler's long-planned ERP upgrade collapsed on go-live day: an incomplete data migration left 2,800 customer records unreadable, order processing halted for 72 hours, and the implementation partner withdrew. We stabilised operations, recovered the data, and completed the upgrade the original team could not.
72hrs
Order processing restored
2,800+
Customer records recovered
18d
Full system stable post-rescue
The Challenge
- The implementation partner executed a hard cutover with no parallel-run period — the legacy system was decommissioned before the new ERP was validated under live order volumes, leaving no fallback when failures emerged on day one.
- An incomplete data migration left 2,800 customer accounts, 950+ product records, and all B2B pricing tiers either missing or corrupted in the new system — staff could not look up, create, or ship a single order.
- Training had been delivered in a single session six weeks before go-live. With no recent practice and a broken system on screen, staff had no path to resume operations while the technical team attempted triage.
- The implementation partner withdrew on day two, citing scope disputes, leaving the business without vendor support at the moment of maximum operational crisis.
The Solution
- ✓Arrived on-site on day three and ran a rapid triage: separated which order types could be processed manually in the interim from those requiring the new system, and restored emergency read-only access to the legacy database to unblock the most urgent shipments.
- ✓Ran a 5-day data recovery sprint — extracted master data from the legacy system's backup, rebuilt 2,800 customer accounts, 950+ product records, and all pricing tiers in the new ERP using a structured migration script with field-level validation at every step.
- ✓Conducted a post-mortem analysis identifying seven root causes of the go-live failure: missing data validation gates, no rollback plan, single-session training, no cutover rehearsal, no hypercare staffing plan, late stakeholder sign-off, and scope creep not flagged before go-live.
- ✓Used the post-mortem findings to redesign the remaining rollout in phases: core order processing live in week two, financial reporting and advanced configuration in week three, with daily reconciliation checkpoints and dedicated on-site support for the first 30 days post-stabilisation.
Key Outcomes
72hrs
Order processing restored
2,800+
Customer records recovered
18d
Full system stable post-rescue
Industry
Wholesale & Distribution
Solution
ERP & Systems Advisory
Client
Lakeshore Food Group Inc.
ERP AdvisoryWholesaleUpgrade Recovery
Ready to see similar results?
Book a Diagnostic →